Installation of the 3rd Machine for Large-diameter GRP pipes. |
|
|
|
Commissioning of the 3rd LDP machine. |
|
|
|
Full-swing
production run for SE/71 project. |
|
|
|
Augmented
the production output for the SE/100 project. |
|
|
|
Al-Watani's third and newest
continuous-filament winding machine is now fully operational. Machine
No. 3 was commissioned in October 2007 and is now capable of producing GRP
pipes and couplers of nominal sizes ranging from DN300 to DN2600.
This third machine acquired from the
Italian Company
|
|
VEM, has boosted Al-Watani's GRP pipe production from 45 pipes to over 70
pipes per day which is equivalent to about 25 to 30 kilometers of pipeline per
month. All of Al-Watani GRP pipes are produced through cutting edge pipe automation
technology backed by experienced operators and GRP technicians.
|